Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

what is the answer to this fraction 4/8+4/8+2/8​
help plz on question 7​
What happened in 150 BC?
What does devised most likely mean? A. read about B. moved toward C. came up with D felt bad about
what refers to the alteration in the structure or function of an organism​
Write the equation of the line, in slope-intercept form, with the following information: slope: -2 y-intercept: (0, -3)
Without the influence of colonialism, would African countries be as ethnically diverse as they are today?
3 ⋅ f (−4) −3 ⋅ g (−2)
Which expression is equivalent to 4sqrt x^10​
Juan's pit crew was able to get his car back onto the racetrack 0.4 seconds faster than Paul's crew. Paul's crew took 1.3 seconds longer than Terry's crew. Terr