a person can do a job in 6 day days . another can do the same job in 4days . if they work together, how long do they need to finish the job?

Respuesta :

wegnerkolmp2741o
wegnerkolmp2741o wegnerkolmp2741o
  • 01-08-2020

Answer:

It will take them 2 2/5 days working together

Step-by-step explanation:

To find the time worked

1/a + 1/b = 1/t

Where a and b are the times worked individually and t is the time worked together

1/4 + 1/6 = 1/t

Multiply each side by 12t to clear the fractions

12t( 1/4 + 1/6 = 1/t)

3t + 2t =12

Combine like terms

5t = 12

Divide by 5

t = 12/5

t = 2 2/5

It will take them 2 2/5 days working together

Answer Link

Otras preguntas

which type of cell has membrane bound organelles
PLEASE TELL ME IF MY ANSWER IS REASONABLE Prompt: Read the letter to the editor "I, Too, Have a Dream." How does the writer use structure and language to persua
Write an informative essay on the topic of immigration. Your essay will use research to describe the changes and challenges that today's immigrant children expe
PLEASE, PLEASE, PLEASE HELP!!!!! WILL GIVE BRAINLIEST, 5-STAR RATING, AND THANK YOU!!!! 8pts guranteed Helpful answers are really appreciated! What was the stea
Enter the correct code 4digit code no space level 5
What even is this???
how do i put a picture on this site? It's not letting me.
What is an example of a physical change during digestion?
How much work is done when a 65 newton force moves a block 5 meters Joules)
The government makes ALL economic decisions. What type of economy is this A. Traditional B.Command C.Market D.Mixed